Construction Update May

Watch Olivine coming together

Construction at Olivine by Mirvac is progressing well with lots happening onsite.

Key construction activity includes:

Stages 1A to 3 are complete
• Stage 4: Sewer and drainage infrastructure complete. Water services nearing completion. Road works have commenced.
• Stage 5A: Sewer and drainage infrastructure complete. Water services nearing completion.
• Stage 1B wetland: 95% complete with planting to commence

Title registration forecast dates are as follows:

•  Stage 1A - Title registration occurred 11 June 2019
• Stages 2 & 3 - Title registration occurred 12 June 2019
• Stage 4 - Titles anticipated November 2019
• Stage 5A - Titles anticipated January 2020
• Stage 9 - Titles anticipated April to May 2020
• Stage 10 - Titles anticipated August to October 2020