Construction Update September 2019

Watch as Olivine Comes to Life

Olivine is a buzz of activity with construction progressing well onsite. 

Key construction milestones at Olivine include:

Stage 4
• Kerb works are currently underway, with all kerb and channel works due for completion over the coming fortnight
• Following this, the first layers of road pavement will be installed and works to footpaths and crossovers will commence thereafter

Stage 5A
• Infrastructure services including drainage, sewer, water and gas have been installed and the road has been excavated
• The road sub base layer is now nearing completion

Stage 9
• Earthworks have been completed and sewer infrastructure installation will be commencing over the coming fortnight

 

Title registration forecast dates are as follows:

• Stage 1A - Title registration occurred 11 June 2019
• Stages 2 & 3 - Title registration occurred 12 June 2019
• Stage 4 - Titles anticipated November 2019
• Stage 5A - Titles anticipated January 2020
• Stage 9 - Titles anticipated April to May 2020
• Stage 10 - Titles anticipated August to October 2020

 

Watch our construction update video below;